Tools Needed:
– 9/16” Wrench(es)

  1. Slide compression nut and acetal ferrule onto molded header. MAKE SURE TO NOTE THE CORRECT ORIENTATION OF THE FERRULE AS SHOWN ON FIGURE 4.
  2. Push molded header of exchanger with acetal ferrule and compression nut all the way into the adapter.
  3. While holding the pushed-in molded header in place to prevent rotation, tighten compression nut to finger tight. FAILURE TO HOLD MOLDED HEADER IN PLACE WHILE TIGHTENING CAN TWIST THE NAFION™ MEMBRANE AND DAMAGE THE BRAIDED EXCHANGER.
  4. With wrench(es), tighten compression nut an additional 1-1/4 turns.


Download BE-HP Series High Pressure Gas Moisture Exchanger User’s Manual